OpenAI Stargate Abilene

Oracle · Abilene, United States

OpenAI Stargate Abilene is a operational data center project in Abilene, United States. This record brings together its location, estimated IT capacity, construction timeline, water-disclosure gaps and original sources.

Epoch AI · Checked 2026-09-15 · Owner confidence: confident

AI data center listed by Epoch AI.

Request water-use information →

Estimated operating IT capacity

421 MW

Source observation: 2026-07-28

Site water use

Not yet verified

No site-level value published in this atlas

Local water stress

Not yet assessed

Regional context has not been added

How to interpret this record. Epoch reports the site as operational; individual buildings may still be under construction. Capacity is an estimate of IT power, not metered electricity consumption. Sources were collected by Epoch AI; inclusion is not independent verification by our team.

From information to action

Ask about this project’s water use.

Request figures, reporting periods and original documents. Edit the draft to reflect your questions and sign it with your name.

A project-specific public email has not been verified. Copy the request and use an official contact channel from the sources below, or suggest a sourced contact through the contribution form.

Read and edit the request

Opening a draft does not send an email. Review it in your email app before sending.

Project timeline

Source notes reproduced from Epoch AI. Future projections are excluded. Status may have changed since the latest observation.

  1. Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete.

  2. Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 and 4 looked complete from the outside on March 24th, we give it another month after Oracle's post for them to be operational. This would also give the buildings a similar 1 year 4 months timeline that Buildings 1 took from land clearing to being operational.

  3. Building 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according to a regulatory filing. Building 5 still has light construction activity, while Building 6 still lacks chillers. The on-site power plant to the right of Building 2 looks complete.

  4. The 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation in 3 months. Building 4 has about 80% of chillers installed. Other buildings have few or no chillers installed.

  5. Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a TDLR filing, but this date is also consistent with satellite imagery. By January 15, Building 2 looked as finished as Building 1, whereas on September 26 it did not look finished.

  6. Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe announcement. While the first phase consists of Building 1 and 2, the language doesn't outright confirm that both buildings are fully operational. The announcement also stated that "Oracle began delivering the first NVIDIA GB200 racks in June", and we think 3 months is enough time to ram to 50,000 GB200s in Building 1. The satellite image also suggests that Building 1 is complete (shell and equipment done, many cars neatly parked) while Building 2 is ongoing (trucks and construction equipment still present). The 200 MW substation built in 2022 and expanded in 2024 is enough to power both buildings. To the right of Building 2, five gas turbines are in place with five more turbines still under construction. Chillers are partly installed for Building 3. Roof is complete for Building 4. The larger 1 GW substation is not complete yet.

  7. Building 1 looks close to finishing construction, with chillers in place. OpenAI stated that "Oracle began delivering the first NVIDIA GB200 racks in June." The "tenant improvement" work is not due until September, however.

  8. Land clearing begins for northern two buildings (Building 1-2)

Location

5502 Spinks Rd, Abilene, TX 79601

View the surrounding area ↗

Sources & further reading

Dataset attribution: Epoch AI, CC BY.

Local context is still being researched

No independently reviewed permit summary or community report has been added here. This does not mean there are no permits, concerns or impacts.

Contribute local knowledge

Help fill in the picture.

Suggest a project, correction or local concern. Include a public source so an editor can review it. Reports are private until reviewed; submitting does not change the map.

We store your contribution and source for editorial review. Please share only information you have permission to submit. We do not ask for your name or email.

Frequently asked questions about OpenAI Stargate Abilene

Where is OpenAI Stargate Abilene?

OpenAI Stargate Abilene is listed at 5502 Spinks Rd, Abilene, TX 79601. The project is in Abilene, United States.

How much power does OpenAI Stargate Abilene use?

The latest source-backed estimate in this atlas is 421 MW of operating IT capacity, observed for 2026-07-28. This is an estimate of computing capacity, not metered annual electricity consumption.

How much water does OpenAI Stargate Abilene use?

No verified site-level water withdrawal or consumption figure has been added to this atlas. A missing figure means the value is not verified here, not that the project uses no water.