Google Columbus is a operational data center project in Columbus, United States. This record brings together its location, estimated IT capacity, construction timeline, water-disclosure gaps and original sources.

Epoch AI · Checked 2026-09-15 · Owner confidence: confident

AI data center listed by Epoch AI.

Request water-use information →

Estimated operating IT capacity

303 MW

Source observation: 2026-08-05

Site water use

Not yet verified

No site-level value published in this atlas

Local water stress

Not yet assessed

Regional context has not been added

How to interpret this record. Epoch reports the site as operational; individual buildings may still be under construction. Capacity is an estimate of IT power, not metered electricity consumption. Sources were collected by Epoch AI; inclusion is not independent verification by our team.

From information to action

Ask about this project’s water use.

Request figures, reporting periods and original documents. Edit the draft to reflect your questions and sign it with your name.

A project-specific public email has not been verified. Copy the request and use an official contact channel from the sources below, or suggest a sourced contact through the contribution form.

Read and edit the request

Opening a draft does not send an email. Review it in your email app before sending.

Project timeline

Source notes reproduced from Epoch AI. Future projections are excluded. Status may have changed since the latest observation.

  1. Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.

  2. Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.

  3. Buildings 1-3 are visibly operational, with steam coming out of the cooling towers. Meanwhile Building 4 is extremely close to completion, with all backup generators complete with only 3 cooling towers missing their fans. ~1/2 the generators are installed for Building 5, and the roof is mostly complete (starting to install the final white layer, with the actual roof structure already complete).

  4. Building 3 operational. Surrounding roads finished, no more visible construction.

  5. Building 2 operational. Parking complete, no more visible construction.

  6. Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.

  7. Building 2 foundation work begins. Building 1 generators seem complete, cooling towers still under construction.

  8. Land clearing begins on the eastern half of the site, for Buildings 1-2

Location

5076 S High St, Columbus, OH 43207

View the surrounding area ↗

Sources & further reading

Dataset attribution: Epoch AI, CC BY.

Local context is still being researched

No independently reviewed permit summary or community report has been added here. This does not mean there are no permits, concerns or impacts.

Contribute local knowledge

Help fill in the picture.

Suggest a project, correction or local concern. Include a public source so an editor can review it. Reports are private until reviewed; submitting does not change the map.

We store your contribution and source for editorial review. Please share only information you have permission to submit. We do not ask for your name or email.

Frequently asked questions about Google Columbus

Where is Google Columbus?

Google Columbus is listed at 5076 S High St, Columbus, OH 43207. The project is in Columbus, United States.

How much power does Google Columbus use?

The latest source-backed estimate in this atlas is 303 MW of operating IT capacity, observed for 2026-08-05. This is an estimate of computing capacity, not metered annual electricity consumption.

How much water does Google Columbus use?

No verified site-level water withdrawal or consumption figure has been added to this atlas. A missing figure means the value is not verified here, not that the project uses no water.