AWS Berwick

Amazon · Berwick, United States

AWS Berwick is a operational data center project in Berwick, United States. This record brings together its location, estimated IT capacity, construction timeline, water-disclosure gaps and original sources.

Epoch AI · Checked 2026-09-15 · Owner confidence: confident

AI data center listed by Epoch AI.

Request water-use information →

Estimated operating IT capacity

108 MW

Source observation: 2026-08-01

Site water use

Not yet verified

No site-level value published in this atlas

Local water stress

Not yet assessed

Regional context has not been added

How to interpret this record. Epoch reports the site as operational; individual buildings may still be under construction. Capacity is an estimate of IT power, not metered electricity consumption. Sources were collected by Epoch AI; inclusion is not independent verification by our team.

From information to action

Ask about this project’s water use.

Request figures, reporting periods and original documents. Edit the draft to reflect your questions and sign it with your name.

A project-specific public email has not been verified. Copy the request and use an official contact channel from the sources below, or suggest a sourced contact through the contribution form.

Read and edit the request

Opening a draft does not send an email. Review it in your email app before sending.

Project timeline

Source notes reproduced from Epoch AI. Future projections are excluded. Status may have changed since the latest observation.

  1. Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.

  2. Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date.

  3. The SRBC increases approved water use from 0.060 MGD to 0.129 MGD. This supports that some expansion is happening, but does not explicitly prove a third operational building.

  4. Building 2 operational estimate. This is based on the progress visible in the September 2025 image. The DEP also issues an air plan approval to add 48 more emergency generators on this date.

  5. Building 1 operational estimate. According to Google Earth Satellite Imagery from this date, Building 1 appears structurally complete and likely operational, while Building 2 is still missing two generators.

  6. Building 1 fit out and related construction begins under Amazon, based on the Susquehanna River Basin Commission (SRBC) schedule.

  7. AWS acquires the Cumulus/Talen building campus for $650M.

  8. Cumulus completes a 48 MW, 300,000 sq ft powered shell for the first data center at the Susquehanna campus. The shell is available for lease, with the campus still awaiting its first tenant and commercial operations.

  9. Land clearing begins. Talen Energy reported on July 12, 2021 that site-preparation permits had already been obtained and site work was underway, while permits for construction of the first building were still being pursued. We model land clearing as starting from the beginning of the month.

Location

1125 Electron Ave, Berwick, PA 18603

View the surrounding area ↗

Sources & further reading

Dataset attribution: Epoch AI, CC BY.

Local context is still being researched

No independently reviewed permit summary or community report has been added here. This does not mean there are no permits, concerns or impacts.

Contribute local knowledge

Help fill in the picture.

Suggest a project, correction or local concern. Include a public source so an editor can review it. Reports are private until reviewed; submitting does not change the map.

We store your contribution and source for editorial review. Please share only information you have permission to submit. We do not ask for your name or email.

Frequently asked questions about AWS Berwick

Where is AWS Berwick?

AWS Berwick is listed at 1125 Electron Ave, Berwick, PA 18603. The project is in Berwick, United States.

How much power does AWS Berwick use?

The latest source-backed estimate in this atlas is 108 MW of operating IT capacity, observed for 2026-08-01. This is an estimate of computing capacity, not metered annual electricity consumption.

How much water does AWS Berwick use?

No verified site-level water withdrawal or consumption figure has been added to this atlas. A missing figure means the value is not verified here, not that the project uses no water.